Fort Lauderdale-Hollywood International Airport Glass Replacement at Terminal 1, Concourse B & C. Work completes in January 2025 at this unique job site. All in-house personnel performed replacement of nearly 2,000 pieces of failed glass. Outdated window walls were modernized and received new glass. During construction all gates within the 17th busiest US airport remained operational thanks to intense planning. Work took place at night to ensure protection of the traveling public, and airline operations. All employees received site safety training, background checks, security badging. To protect daytime operations, Timekey completely demobilized daily, checking in all tools and material upon arrival for safety, and removing all debris, tools and equipment daily to avoid conflict with airline operations. Despite heat, rain, and a host of interested onlookers and stakeholders, Timekey will finish early to very happy customers across the project team.